3.3.3 01 Change Management Due to System Change

Change Management Due to System Change / Ohio DOT

In fiscal year 2016, ODOT began phasing in new requirements for the development of District Work Plans that combined Capital and Maintenance projects. At that time, Districts’ Work Plans were required to match 25 percent of the lower cost treatments (such as chip seals and micro-surfacing) recommended by the pavement management system. For FY2017 and beyond, District Work Plans are required to match 75 percent of these PMS recommendations.

This change was met with concern by some district staff in regards to data quality in the PMS, and lack of familiarity with the new process. To address staff concerns, the Asset Management Leadership Team conducted workshops, bringing in staff involved in pavement programming from across the state. The workshop focused on actions that Ohio DOT could take to improve the PMS and its programming processes.